July Capital Project Update: Major progress made!
Posted on 07/10/2020
 |
Dry summer weather and efficient work by Campus Construction have helped move along several different jobs at a few different schools in our Renewal Project. Here are some highlights:
Irondequoit High School
- Roof replacement is nearly complete; metal flashing work will be on-going in July and August.
- The gymnasium floor has been removed and new hoops installed; installation of the new floor will begin soon.
- Demolition on the front (main) entrance foyer/vestibule began in late June, right after graduation ceremonies wrapped up. New security walls will be built in July; doors also will be replaced.
- Locker room renovations are down to the final stages; tile work should end before school starts.
Dake Junior High School
- Concrete work outside was completed in June.
- Major renovations of the main office are moving along well; painting and floor prep is scheduled for July.
- Renovations/framing of the new main entrance vestibule also are under way.
Iroquois Middle School
- Roof work is complete.
- Classroom carpet replacement is on-going.
- New concrete will be poured for a walkway on the building’s east side.
Rogers Middle School
- Work on walls in the basement corridor has begun
- New carpet installation begins later in July
Colebrook & Southlawn
- New playgrounds were completed and re-opened in June.
For all Capital Project updates, visit our page at this link. |